Construction of Biomass Power Plant Project Using Palm Empty Fruit Bunch
in Sumatra island, Indonesia

This project also has been certified as a bilateral credit system (JCM) facility subsidy project by the Japanese
Ministry of the Environment.

LocationAceh Province, Sumatra Island, Indonesia
Capacity12MW
Start OperationScheduled in 2024
Predicted GHG
emission
reduction amount
31,322 tCO2/year

Reference emissions
Annual estimated power generation x Grid
emission factor 34,765 tCO2/year

Project emissions
CO2 emissions from fossil fuel consumption
at biomass power plant.
CO2 emissions during biomass
transportation 3,443 tCO2/year

Construction of 2MW Mini-Hydro Power Plant Project in East Nusa Tenggara, Indonesia

This project also has been certified as a bilateral credit system (JCM) facility subsidy project by the Japanese
Ministry of the Environment.

LocationEast Nusa Tenggara Province, Indonesia
Capacity2MW
Start OperationScheduled in 2024
Reference
Emission
6,856 tCO2/year
Project Emissions0